How to Calculate Critical Path, Float, Early Start & Late Start, and Early Finish & Late Finish


train-setThis is a part-post from Developing Project Schedule project management activity post. You will learn how to calculate critical path, float/slack, early & late starts, and early & late finishes of a network path in this article.

For easier understanding this post is divided into four parts that can be navigable at the bottom of each part.

I suggest you get yourself a cup of your favorite beverage (I was going to say Coffee), this one is going to be a long ride. 🙂

As we saw in Developing Project Schedule project management activity, Critical path is made up of series of activities from beginning to the end, where each activity has a dependency over previous activity in such a way that delay in any one activity causes delay in all subsequent activities, causing the project to slip.

Click here to get my PMP exam brain-dump for free.

In other words, critical path is the longest path in your project’s schedule network diagram, and is the SHORTEST possible duration for the project.

How to Calculate Critical Path

Let us take a simpler example than John’s home construction example we saw in previous lessons. This project involves assembling a train set (refer to the picture above).

Calculating Critical Path is a simple 4-step process.

Step 1: Find Activities

Activities for this project are as below (output from Define Activities process) –

A. Assemble two-tier bridge B. Join winding tracks C. Assemble and add train station D. Place standalone items around E. Assemble and add construction site F. Join train engine and bogies G. Place the train on the track H. Start the engine and let it chug!

Step 2: Build Schedule Network Diagram

Sequence activities and build schedule network diagram (output from Sequence Activities process) . This is how it looks, with individual activity duration in minutes –

critical-path-trainsetFigure 2: Assemble train set – schedule network diagram

Step 3: Find all Possible Paths

Find all possible paths through the diagram, there are 3 in our case –

A -> B -> F -> G -> H

A -> B -> C -> D -> G -> H

A -> B -> C -> E -> G -> H

Step 4: Calculate Duration for Each Path

Let us see the duration for each of these paths –

A -> B -> F -> G -> H —> 10+20+4+2+2 = 38 minutes

A -> B -> C -> D -> G -> H —> 10+20+5+10+2+2 = 49 minutes

A -> B -> C -> E -> G -> H —> 10+20+5+2+2+2= 41 minutes

The network path with longest total duration is the critical path!

Critical path is the shortest duration required to complete the project successfully.

In our example this is the second path:  A -> B -> C -> D -> G -> H, which comes to 49 minutes.

critical-path-firstpathFigure 3: Assemble train set – Critical Path

Note that sum of durations of all activities on critical path comes 49 minutes, and sum of duration of ALL activities on the project is much longer. If managed well, the whole project can be completed within the critical path’s duration.

In the next page, let us see how to calculate Float for activities.. (please use the page numbered link below to navigate)..

Recommended by Google

{ 30 comments… add one }
  • base_speed April 8, 2014, 7:35 pm

    thank you very much, it greatly helped…

    Reply
    • Shivshanker Shenoy April 9, 2014, 6:28 pm

      I’m glad you found this useful!
      -Shiv

      Reply
    • Tony July 13, 2016, 6:07 am

      Thank you for the free service

      Reply
  • NOni May 31, 2014, 5:25 am

    Thanks 2 much Mr. Shiv.

    I was realy need it.

    Reply
  • 555PPS June 10, 2014, 10:21 am

    Is the calculation in Step3/figure5 correct?
    I can’t see the path with a duration of 31.

    Reply
    • Shivshanker Shenoy June 10, 2014, 2:29 pm

      Hi! Thanks so much for pointing out the typo, I have fixed it now.
      Regards,
      Shiv

      Reply
  • Nick August 27, 2014, 6:58 am

    Major error on page 4. Critical path is the LONGEST path out of all paths in the specific precedence network. You have it listed as shortest.

    Reply
    • Shiv Shenoy August 27, 2014, 4:31 pm

      Nick, the longest path through network diagram is the critical path – which is the shortest path for the completion of the project.

      Reply
  • json crown October 27, 2014, 5:08 pm

    great written practical illustration

    Reply
  • aaaaa December 27, 2014, 7:49 pm

    Wonderful. Helped me a lot. Thanks

    Reply
  • khadar January 27, 2015, 12:19 am

    thank you for your help

    Reply
  • Hamed Barhumi March 12, 2015, 2:54 pm

    Hi Shiv, hope you are doing fine, I would appreciate sending me your posts to my e-mail, im applying for PMP certification & interseted in project scheduling hints & Tips..

    Yours,
    Hamed B.

    Reply
    • Shiv Shenoy March 17, 2015, 5:49 pm

      Hi Hamed, please refer to the Start Here page from the menu above. You can also schedule a free Skype call with me using button at the bottom of this page. Over this call we can discuss what should be your examination approach, and I can share few tips that might be useful.

      Cheers,
      Shiv

      Reply
  • MOHIT CHUGH November 17, 2015, 4:45 pm

    seriously helped me alot. thank u so much

    Reply
    • Shiv Shenoy November 18, 2015, 9:43 am

      Hi Mohit,
      Glad to see you are finding these useful.
      Best wishes for the exam!
      Best,
      Shiv

      Reply
  • Bhushan April 11, 2016, 12:28 am

    Wonderful, doubt if one can find anywhere anything better on the above subject on the net.
    Great work Shiv, thank you so much, keep up the good work.

    Regards,
    Bhushan

    Reply
    • Shiv Shenoy April 19, 2016, 12:34 pm

      Hey Bhushan, am glad to know you are finding these notes useful.

      Good luck!
      Shiv

      Reply
  • M. Gibson January 10, 2017, 1:18 pm

    Very useful example

    Reply
  • Bernard Bartholomew January 21, 2017, 9:12 am

    Thanks a lot of shiv this was more than helpful me. You have done a great job. May continue to wax strong.

    Reply
  • Shannon February 5, 2017, 9:15 pm

    I was really impressed with the easy to understand breakdown. Both the written explanation, diagrams, and videos were very comprehensive and easy to follow. There were no gaps in the explanation and demonstrations. Huge help to me. Thank you~

    Reply
    • Shiv Shenoy February 6, 2017, 7:36 pm

      Thank you Shannon, for the kind words. I’m glad to see that you are finding this useful!
      Best,
      Shiv

      Reply
      • magy danny April 5, 2017, 1:45 pm

        thanks so much for that good example

        Reply
  • Pankaj April 28, 2017, 9:45 am

    Hi Shiv,
    Just started to read your posts, feel you have done amazing work.
    Post going through your posts, i believe this could substitute all the trng materials out there 🙂

    Regards,
    Pankaj

    Reply
    • Shiv Shenoy May 1, 2017, 6:25 pm

      Thank you Pankaj, that is the idea! 🙂

      Cheers,
      Shiv

      Reply
  • http://raovatmang.net/ January 2, 2018, 5:39 am

    I’m not sure where you’re getting your information, but great topic.
    I needs to spend some time learning more or understanding
    more. Thanks for great info I was looking for this information for my mission.

    Reply
Cancel reply

Leave a Comment